From: Lucarelli,
Zachary <Zachary.Lucarelli@skanska.com>
Sent: Wednesday,
November 12, 2025 12:01 PM
To: Pang,
Jason (Consultant); Tu, Sammy; Pollack, Allie; Prendergast, Patrick
Cc: Berriz,
Sonia (Consultant); Kane, Betty (Consultant); Pao, Evelyn C.; Holmquist, Dan
(Consultant); Wolf, Hayden; Gaffney, Erin; Snyder, Daniel; Barrios, Josh
Subject: Re:
[EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating & Inspection
Jason,
Danny just opened the
vault and sounds like we have 5' or so of water. We estimate that we can get it
down to 12" or so by 12PM tomorrow. We can do an inspection in the AM to
confirm pumping progress. If we can setup the inspection for 2PM, that would be
great.
Please have Duncan
coordinate with me or Danny for details. We are fine with WSDOT BPO inspectors
heading to the vault, so long as they notify our team they are onsite.
Thanks,
Zach
From: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Sent: Wednesday, November 12, 2025 11:55 AM
To: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>;
Tu, Sammy <sammy.tu@aecom.com>;
Pollack, Allie <Allie.Pollack@aecom.com>;
Prendergast, Patrick <Patrick.Prendergast@skanska.com>
Cc: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Kane, Betty (Consultant) <Betty.Kane@consultant.wsdot.wa.gov>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Wolf, Hayden <hayden.wolf@wsdot.wa.gov>;
Gaffney, Erin <erin.gaffney@skanska.com>;
Snyder, Daniel <Daniel.Snyder@skanska.com>
Subject: RE: [EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating
& Inspection
Zach,
Our inspector can come at 9a tomorrow or later in the day if more time is needed to pump the vault. Please let me know what time is possible to gain access and what you find out today. Please let us know any other logistics to gain access. I am going to put Duncan in contact with Betty and can go from there.
Thanks
Jason
From: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Sent: Tuesday, November 11, 2025 10:39 AM
To: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>;
Tu, Sammy <sammy.tu@aecom.com>;
Pollack, Allie <Allie.Pollack@aecom.com>;
Prendergast, Patrick <Patrick.Prendergast@skanska.com>
Cc: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Kane, Betty (Consultant) <Betty.Kane@consultant.wsdot.wa.gov>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Wolf, Hayden <hayden.wolf@wsdot.wa.gov>;
Gaffney, Erin <erin.gaffney@skanska.com>;
Snyder, Daniel <Daniel.Snyder@skanska.com>
Subject: Re: [EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating
& Inspection
Jason,
WSDOT BPO visited the site and went inside the vault several months ago, is this inspection in addition to that visit that already happened? If my memory serves me correctly - I think this was in June/July of this year.
Thanks,
Zach
From: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Sent: Tuesday, November 11, 2025 9:07 AM
To: Tu, Sammy <sammy.tu@aecom.com>; Lucarelli, Zachary
<Zachary.Lucarelli@skanska.com>; Pollack, Allie <Allie.Pollack@aecom.com>; Prendergast, Patrick
<Patrick.Prendergast@skanska.com>
Cc: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>; Kane, Betty
(Consultant) <Betty.Kane@consultant.wsdot.wa.gov>; Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>; Holmquist, Dan
(Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>; Wolf, Hayden <hayden.wolf@wsdot.wa.gov>
Subject: RE: [EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating
& Inspection
WSDOT will be conducting their own inspection.
Thanks Sammy
From: Tu, Sammy <sammy.tu@aecom.com>
Sent: Tuesday, November 11, 2025 8:10 AM
To: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>;
Pollack, Allie <Allie.Pollack@aecom.com>;
Prendergast, Patrick <patrick.prendergast@skanska.com>
Cc: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Kane, Betty (Consultant) <Betty.Kane@consultant.wsdot.wa.gov>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Wolf, Hayden <hayden.wolf@wsdot.wa.gov>
Subject: [EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating &
Inspection
WARNING: This email originated from outside of WSDOT. Please use caution with links and attachments.
Hi Jason,
The QA was completed yesterday, and the report is on its way to WSDOT. It has been sealed and is being submitted with electric files as requested.
The inspection was conducted by RHC in accordance with WSDOT BDM and NBI regulations. Please refer to PDF pages 147 through 158 of 215. Note that the inspection was performed by a WSDOT-certified inspector and the report was included in previous submittals.
I hope this helps facilitate WSDOT’s approval. Please don’t hesitate to reach out if you have any questions or need further information.
Best regards,
Sammy Tu, P.Eng, PE, SE
C: 510-410-9326
From: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Sent: Monday, November 10, 2025 8:46 AM
To: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>;
Tu, Sammy <sammy.tu@aecom.com>;
Pollack, Allie <Allie.Pollack@aecom.com>;
Prendergast, Patrick <patrick.prendergast@skanska.com>
Cc: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Kane, Betty (Consultant) <Betty.Kane@consultant.wsdot.wa.gov>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Wolf, Hayden <hayden.wolf@wsdot.wa.gov>
Subject: I-405 Brickyard - NW-12 Load Rating & Inspection
Sammy/Zach Are we getting the final load rating so I can send to the Bridge Office for their review and acceptance? We discussed receiving it last Friday. It would be sad to see further delay of switching traffic because of QA and submittal.
Sammy/Zach
Are we getting the final load rating so I can send to the Bridge Office for their review and acceptance? We discussed receiving it last Friday.
It would be sad to see further delay of switching traffic because of QA and submittal. Reminder - Please be sure to send it signed and sealed, with electronic files, and following BDM 13.4.
The initial inspection (BDM 10.13) also needs to be completed. With the short notice of a target opening, hopefully they can get in there next week to inspect. I will hear back this week and then will need to coordinate with you on access.
Thanks
Jason
From: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Sent: Wednesday, November 5, 2025 2:00 PM
To: Tu, Sammy <sammy.tu@aecom.com>;
Pollack, Allie <Allie.Pollack@aecom.com>
Cc: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Subject: [EXTERNAL] Re: RE: RE: I-405 Brickyard - NW-12 Load Rating
- OTS
WARNING: This email originated from outside of WSDOT. Please use caution with links and attachments.
Confirmed. Plates will be 1".
Zach
From: Tu, Sammy <sammy.tu@aecom.com>
Sent: Wednesday, November 5, 2025 11:38 AM
To: Pollack, Allie <Allie.Pollack@aecom.com>
Cc: Pang, Jason (Consultant) <jason.pang@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Subject: FW: RE: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Hi Allie,
Jason confirmed closure of the OTS comments during this morning’s task force meeting — thanks to Jason for wrapping that up.
Please update page 166 with the following:
This email serves as confirmation that the OTS comments have been closed, and please move forward the QA process
Regards,
Sammy Tu, P.Eng, PE, SE
C 510-410-9326
From: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Sent: Tuesday, November 4, 2025 9:25 PM
To: Tu, Sammy <sammy.tu@aecom.com>
Cc: Pollack, Allie <Allie.Pollack@aecom.com>
Subject: RE: RE: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Sammy, I agree with you on the barrier that the load is minimal or negligible for the lane configuration shown. I thought there were different MOT switches or where the roadway starts to move back off the vault that the barrier was midspan and
Sammy,
I agree with you on the barrier that the load is minimal or negligible for the
lane configuration shown. I thought there were different MOT switches or where
the roadway starts to move back off the vault that the barrier was midspan and
lane on each side. Someone had shared a figure. Perhaps it changed or I missed
something?
I agree with your responses and will go take a look at Zach’s response for last bullet.
Thanks
Jason
From: Tu, Sammy <sammy.tu@aecom.com>
Sent: Tuesday, November 4, 2025 7:06 PM
To: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Cc: Pollack, Allie <Allie.Pollack@aecom.com>
Subject: [EXTERNAL] RE: RE: I-405 Brickyard - NW-12 Load Rating -
OTS
WARNING: This email originated from outside of WSDOT. Please use caution with links and attachments.
Hi Jason,
I’ve revised page 166 to specify a 1” cover plate for all openings.
Could you please provide your feedback to our responses, so we can proceed with Lead verification and the QA process for the submittal? If needed, we’re available for a coordination meeting tomorrow morning after TFM.
Thanks,
Sammy Tu, P.Eng, PE, SE
C 510-410-9326
From: Pollack, Allie <Allie.Pollack@aecom.com>
Sent: Monday, November 3, 2025 1:16 PM
To: Tu, Sammy <sammy.tu@aecom.com>; Pang,
Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>;
Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Abraham, Ryan <ryan.abraham@aecom.com>;
Guerrero, Jon <Jon.Guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Viriyincy, Gavin <Gavin.Viriyincy@aecom.com>
Subject: RE: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Hi Jason,
Please see below for our responses to your comments.
Thanks,
Allie
Allie Pollack, EIT
Structural Bridge Engineer, US West Transportation
allie.pollack@aecom.com
AECOM
1111 3rd Avenue
Suite 1600
Seattle, WA 98101, United States
Delivering a better world
LinkedIn | Twitter |
Facebook |
Instagram
From: Tu, Sammy <sammy.tu@aecom.com>
Sent: Monday, November 3, 2025 11:09 AM
To: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>;
Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Abraham, Ryan <ryan.abraham@aecom.com>;
Guerrero, Jon <Jon.Guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Pollack, Allie <Allie.Pollack@aecom.com>
Subject: RE: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Jason,
That’s great news. We will revise the report and submit it asap.
Regards,
Sammy Tu, P.Eng, PE, SE
C 510-410-9326
From: Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Sent: Monday, November 3, 2025 11:05 AM
To: Tu, Sammy <sammy.tu@aecom.com>; Berriz,
Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Abraham, Ryan <ryan.abraham@aecom.com>;
Guerrero, Jon <Jon.Guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Pollack, Allie <Allie.Pollack@aecom.com>
Subject: RE: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Hi Sammy, No additional comments from the Project Office on the OTS. The Bridge Office will review the formal submittal to WSDOT and grant Final Approval as appropriate per BDM 15. 12. 1 Thanks Jason From: Tu, Sammy <sammy. tu@ aecom. com>
Hi Sammy,
No additional comments from the Project Office on the OTS. The Bridge Office will review the formal submittal to WSDOT and grant Final Approval as appropriate per BDM 15.12.1
Thanks
Jason
From: Tu, Sammy <sammy.tu@aecom.com>
Sent: Monday, November 3, 2025 8:55 AM
To: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>;
Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Abraham, Ryan <ryan.abraham@aecom.com>;
Guerrero, Jon <Jon.Guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>;
Pollack, Allie <Allie.Pollack@aecom.com>
Subject: [EXTERNAL] RE: I-405 Brickyard - NW-12 Load Rating - OTS
WARNING: This email originated from outside of WSDOT. Please use caution with links and attachments.
Hi Sonia,
As we continue working through the current set of comments, could you please check if we should expect any additional feedback from other WSDOT reviewers?
Thanks,
Sammy Tu, P.Eng, PE, SE
C 510-410-9326
From: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>
Sent: Friday, October 31, 2025 6:23 AM
To: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Abraham, Ryan <ryan.abraham@aecom.com>;
Guerrero, Jon <Jon.Guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Tu, Sammy <sammy.tu@aecom.com>;
Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Subject: RE: I-405 Brickyard - NW-12 Load Rating - OTS
Hi all, I wanted to keep everyone on the same page. Jason and Sammy spoke through the OTS comments on NW-12 load rating at their call yesterday and then Jason sent the following over. We are hoping these can be addressed prior to the formal
Hi all,
I wanted to keep everyone on the same page. Jason and Sammy spoke through the OTS comments on NW-12 load rating at their call yesterday and then Jason sent the following over. We are hoping these can be addressed prior to the formal submission.
I think Sammy is able to address most of the comments, I believe coordination is needed with Skanska on the last bullet.
-Sonia
Sonia Berriz, P.E.
berrizs@consultant.wsdot.wa.gov
(425) 876-6283 (cell)
From: Lucarelli, Zachary <Zachary.Lucarelli@skanska.com>
Sent: Tuesday, October 21, 2025 4:01 PM
To: Berriz, Sonia (Consultant) <Sonia.Berriz@consultant.wsdot.wa.gov>
Cc: Prendergast, Patrick <Patrick.Prendergast@skanska.com>;
Sharrer, Kyle <Kyle.Sharrer@skanska.com>;
Tu, Sammy <sammy.tu@aecom.com>;
Ryan Abraham <Ryan.Abraham@aecom.com>;
Guerrero, Jon <jon.guerrero@aecom.com>;
Pao, Evelyn C. <evelyn.pao@wsdot.wa.gov>;
Holmquist, Dan (Consultant) <Dan.Holmquist@consultant.wsdot.wa.gov>;
Pang, Jason (Consultant) <Jason.Pang@consultant.wsdot.wa.gov>
Subject: [EXTERNAL] I-405 Brickyard - NW-12 Load Rating - OTS
WARNING: This email originated from outside of WSDOT. Please use caution with links and attachments.
Sonia,
Below is a link to an OTS of the NW-12 load rating performed by AECOM. Please let us know if you have any questions. I believe this is the right group, cc'd here.
Due to the file size, please confirm confirmation of receipt.
I405-BRICKYARD-NW12
CULVERT LOAD RATING EVALUATION REPORT (draft).pdf
Please ignore the previous messages, where this failed to send due to file size.
Thanks,
Zachary Lucarelli, P.E.
Skanska USA Civil West
18911 North Creek Parkway, Suite 300
Bothell, WA 98011
|
(206) 450-9098
|
|
![]()